Case files · 23 November 2026
Latest File · Brickell & Brickell KeyFollowing a building in these files?Tell Josh which one. He’ll send its recorded sales from the Miami-Dade record, what is on the market there now …Open the files →
Josh Stein, Miami real estate associateJosh Stein
Aerial view over Coral Gables with the Biltmore tower, golf course and tile-roofed houses under the tree canopy

The Avenue Coral Gables

Verified 26 August 2026Property Search5 sources

Sources

1 / 2

An aerial over Coral Gables with the Biltmore tower and tile roofs — the area where The Avenue Coral Gables is located

2 / 2

An avenue of royal palms in Coral Gables, the district around The Avenue Hotel & Residences

Building facts

Address
351 San Lorenzo Avenue, Coral Gables, FL 33146
Neighborhood
Coral Gables
Year built
Not delivered — no completion confirmed
Floors
8
Residences
48
Status
Under construction — broke ground 1 Nov 2023, foundation poured April 2024; no completion confirmed
Developer
Roger Development Group
Architect
Bermello Ajamil & Partners
Pricing
$730,000 to $1,300,000+
An aerial over Coral Gables with the Biltmore tower and tile roofs — the area where The Avenue Coral Gables is located

The Avenue Hotel & Residences Coral Gables — Facts

Address
351 San Lorenzo Avenue, Coral Gables, FL 33146 — opposite the entrance to the Shops at Merrick Park
What it actually is
A hotel and residences, not a condominium building. The full name is The Avenue Hotel & Residences, and the hotel is central to how it works
Status
Under construction. Broke ground 1 November 2023, foundation poured April 2024. Completion was targeted for early 2025; it is now marketed for 2026 and no completion has been confirmed as of 26 August 2026
Stories
8 (the template box says 9)
Residences
48 per the developer and architect at groundbreaking. Some listings say 54 — the discrepancy is unresolved and worth asking about
Residence sizes
598 to 1,200 sq ft, one- and two-bedroom, delivered fully furnished
Pricing
$730,000 to over $1,300,000
Sold
More than 75% as at the November 2023 groundbreaking (65% in July 2023)
Developer
Roger Development Group (Oscar Roger, president and chief executive, with Oscar Roger Jr.)
Architect
Willy Bermello, Bermello Ajamil & Partners · interiors Adriana Hoyos Design Studio · contractor Thornton Construction
Retail
About 3,800 sq ft on the ground floor, in six retail condominium units — all reported sold
County record
No parcel is indexed at 351 San Lorenzo Avenue. See below

Key Takeaways

  • This page never mentioned the hotel, and the hotel is the whole point. The building is The Avenue Hotel & Residences. Owners can live in their home or let it on an annual lease.
  • The specification box does not match the development team’s own numbers. It says 9 stories and 54 units; at the groundbreaking the developer and architect described 8 stories and 48 residences. Some listings do say 54. The discrepancy is unresolved — get the number from the current offering documents.
  • Note: Completion has slipped by at least a year and a half and is unconfirmed. Ground was broken on 1 November 2023 for delivery in early 2025. The foundation was poured in April 2024. As of 26 August 2026 I can find no completion or certificate-of-occupancy report, and the project is now marketed for 2026.
  • It was already more than 75% sold at groundbreaking, and all six ground-floor retail condominium units are reported sold. Whatever is left is a small remainder of a small building.
  • 48 fully furnished residences of 598 to 1,200 square feet, from $730,000 to over $1.3 million, across the street from the Shops at Merrick Park, by Roger Development Group with Willy Bermello as architect and Adriana Hoyos on interiors.
  • Note: No county record exists for the site. The Property Appraiser indexes no parcel at 351 San Lorenzo Avenue, so there is no assessed value, no recorded sale and no comparable for this building.
  • Bought pre-construction at The Avenue Coral Gables? — before closing, a sale is usually an assignment of your purchase contract, and whether that is allowed depends on its assignment clause; after closing it is an ordinary resale. Ask Josh what your unit could sell for at delivery on WhatsApp.

The hotel is the point

This page has described The Avenue as a Coral Gables condominium. It is The Avenue Hotel & Residences, and the distinction is the reason to be interested in it.

A buyer here has two options with their home: live in it full time, or let it on a conventional annual lease.

Homes are 598 to 1,200 square feet, one and two bedrooms, delivered fully furnished.

An avenue of royal palms in Coral Gables, the district around The Avenue Hotel & Residences

What this page had wrong

The specification box at the top of this page gives 9 stories and 54 units. At the groundbreaking on 1 November 2023, the developer and the architect described an eight-story building with 48 residences, and Florida YIMBY reported it that way.

I have not been able to reconcile the two. Some listing sources do quote 54 fully furnished units, so it is possible the count changed during design, or that the higher figure includes something the 48 does not — the six ground-floor retail condominiums, for instance, are separate units in their own right. Rather than pick a number, I am telling you both and telling you which is better sourced: 48, from the developer and architect at the groundbreaking. If you are buying, take the count from the current offering documents and nowhere else.

The rest of the specification is consistent across sources and worth stating plainly. Residences run 598 to 1,200 square feet in one- and two-bedroom layouts, fully furnished, with Italian kitchens and baths and Miele, Sub-Zero or Wolf appliances. Prices ran from $730,000 to over $1.3 million. There is a resort-style pool deck with a summer kitchen and dining area at the top of the building, valet parking, and hotel front-desk service. On the ground floor there is about 3,800 square feet of retail in six condominium units, all of which have been sold.

The design is Parisian-inspired neo-classical — a deliberate fit with the Mediterranean-revival vocabulary Coral Gables enforces on new building, and a long way from the glass towers going up elsewhere in the county.

Where construction actually stands

The verifiable sequence is short:

  • July 2023 — reported 65% sold.
  • 1 November 2023 — groundbreaking, with more than 75% sold. Completion was then expected in early 2025.
  • April 2024 — foundation poured.
  • Since then — no topping-off report, no completion report, no certificate-of-occupancy report that I can find in the development trade press.

Current marketing describes the building as available for 2026. As of 26 August 2026 I have found nothing confirming that it has been delivered.

I am not suggesting anything is wrong. Small projects often attract little trade coverage once construction is under way. But a delivery date that has moved from early 2025 into 2026 without public confirmation is a fact a buyer should hold, and the remedy is documentary rather than journalistic: ask for the certificate of occupancy, or for the current construction schedule from the general contractor.

No county record for the site

On 26 August 2026 I searched the Miami-Dade County Property Appraiser for 351 San Lorenzo Avenue in every address format the index accepts. It returns nothing. I then swept every street number from 300 to 415 on San Lorenzo Avenue; only two parcels came back, both large Merrick Plat holdings of roughly 69,893 square feet associated with the Merrick Park complex opposite — not this site, which has been described as an 11,000 square foot lot.

So there is no folio, no assessed value, no recorded sale and no comparable available for The Avenue. That is unsurprising for a building still under construction whose condominium declaration has not been recorded, but it has a practical consequence: every price attached to this building is a developer or listing figure, and none of it can be checked against the public record. When the building completes and the declaration records, real numbers will go on this page.

It also means the ordinary trick of looking up what a neighbour paid is unavailable. If you want price context in Coral Gables today, it has to come from recorded sales in comparable finished buildings, which I can pull for you.

What to establish before you buy here

  • The certificate of occupancy, or the contractor’s current schedule. The target has moved from early 2025 to 2026 without public confirmation.
  • The residence count and your unit’s exact size, from the offering documents — 48 and 54 are both in circulation.
  • The association budget calculated on hotel-style operation, not residential. Turnover, housekeeping, front-desk staffing and wear all cost money, and early estimates on hotel-condominiums are frequently revised upward after turnover.
  • What is included in “fully furnished”, and who replaces it when it wears out.

The Avenue is a well-conceived small building in a genuinely excellent Coral Gables location, doing something the rest of the city cannot easily do. The work for a buyer now is entirely in the paperwork: the current schedule and the real unit count — none of which is answerable from a website, including this one.

Already bought at The Avenue Coral Gables?

If you signed a pre-construction contract here, this part of the page is for you: what you can do with your contract, and how to get the record as it changes.

Your three options

  1. Close and keep it. Live in it, or rent it out within the condominium’s rental rules.
  2. Assign your contract before closing. A new buyer takes over your contract. Whether that is allowed, and at what fee, depends on your contract’s assignment clause and usually on the developer’s written consent.
  3. Close, then resell. After closing it is an ordinary resale, priced against what similar homes have actually recorded.

What I will send you

Tell me your unit. I will send you the project’s status from the public filings as it changes, the first recorded sales here when they land, and a straight read on whether to hold, assign or sell.

WhatsApp Josh as an owner

Or send a message

Prefer email? hello@joshsteinrealtor.com

Josh Stein, Florida real estate sales associate, license SL3057661.

The Avenue Coral Gables — Frequently Asked Questions

I bought pre-construction at The Avenue Coral Gables. Can I sell before or at delivery?

It depends on your purchase agreement. Before closing, selling usually means assigning your contract to a new buyer, which developers often allow only with their written consent and sometimes for a fee, so read the assignment clause first. After closing it is an ordinary resale, priced against what similar homes in the building and nearby have actually closed for. If you bought at The Avenue Coral Gables and want to know what your unit could sell for at delivery, message Josh Stein on WhatsApp at (305) 695-8257.

How many residences does The Avenue Coral Gables have?

The developer and architect described 48 residences over 8 stories at the November 2023 groundbreaking, and that is the better-sourced figure. Some listing sources quote 54, and the specification box on this page said 9 stories and 54 units. The discrepancy is unresolved — take the count from the current offering documents.

Is The Avenue Coral Gables finished?

Not confirmed. It broke ground on 1 November 2023 with completion expected in early 2025, and the foundation was poured in April 2024. Current marketing describes it as available for 2026, but as of 26 August 2026 no completion or certificate-of-occupancy report could be found in the development trade press. Ask for the certificate of occupancy or the contractor’s current schedule.

What do homes at The Avenue Coral Gables cost?

Residences were priced from $730,000 to over $1.3 million, at 598 to 1,200 square feet, one and two bedrooms, delivered fully furnished. The building was more than 75% sold at groundbreaking in November 2023, so remaining availability is limited. No recorded sale price exists yet — the county has issued no folios for the site.

Where exactly is The Avenue Coral Gables?

351 San Lorenzo Avenue, Coral Gables, Florida 33146, directly opposite the entrance to the Shops at Merrick Park. Note that the Miami-Dade County Property Appraiser indexes no parcel at that address, so it cannot be looked up in the county’s property search.

Who is developing The Avenue Coral Gables?

Roger Development Group, led by Oscar Roger with Oscar Roger Jr. The architect is Willy Bermello of Bermello Ajamil & Partners, interiors are by Adriana Hoyos Design Studio and Thornton Construction Company is the general contractor. The design is Parisian-inspired neo-classical, in keeping with Coral Gables’ architectural controls.

Is there retail in the building?

Yes — about 3,800 square feet on the ground floor, divided into six retail condominium units, all of which have been reported sold. That is worth knowing as a resident, because the ground-floor tenants are owned by third parties rather than controlled by the residential association.

Sources and further reading

Thinking about The Avenue Coral Gables?

I will get you the offering documents, the current construction schedule and the real residence count before you commit.

ASK JOSH ABOUT THE AVENUE

Thinking about The Avenue Coral Gables?

I have sold South Florida property since 2002. Ask me for the recorded declaration, what has genuinely closed, or a straight answer on whether this building fits what you are after.

Call (305) 695-8257Send me a question

Josh Stein · Florida real estate sales associate, license SL3057661 · (305) 695-8257 · hello@joshsteinrealtor.com
Ask me about The Avenue Coral Gables351 San Lorenzo AvenueWhatsAppContact

South Florida New Construction · Coral Gables · The Avenue Coral Gables

This page never mentioned the hotel, and the hotel is the whole point.

By Josh Stein · Florida license SL3057661 · Updated 22 November 2026Leer en español →

New construction near Coral Gables

21 listings

Listing information is deemed reliable but is not guaranteed and is provided exclusively for consumers' personal, non-commercial use. Data is supplied by the MLS and may be subject to change or withdrawal without notice.

Last updated November 23, 2026, 6:16 pm

Planted by IDX Bloom

Recently sold in Coral Gables

4 listings

Talk to a human

Want to know more?

Drop your details and we will get right back to you.

Related coverage

Part of South Florida New Construction.

Get this building’s public record before you put down a deposit

  • Its permits, approvals and construction status as they appear in city and county filings, each with its filing date.
  • An alert when the status changes, and when the first closed sales in the building are recorded.
  • No sales pitch, no inventory blasts. One building, and only what the public record shows.

Get the building record

Tell Josh which building. He’ll send what the filings show and let you know when it changes.

Direct line

Ask Josh a question

Tell me the building, the budget and the timeline. You will get an honest read, including when the answer is that you should not buy it.

+1 (305) 695-8257 · hello@joshsteinrealtor.comPhone or WhatsApp · English / Español · Licensed in Florida since 2002

The Miami Confidential

The reporting, every two weeks.

Every new case file. Every delivery date that moves. Every figure dated and sourced. No listings, no hype, no press releases dressed up as news.