How to Verify a Miami Pre-Construction Delivery Date in Ten Minutes

A method, not an opinion

4Public records that settle it
10 minRoughly what this takes
22 of 38Towers we track that have moved a date
$0Cost of every source below

Every record in this method is public. None of it requires a licence, a subscription or a phone call.

Buyers ask me whether a pre-construction tower will deliver on time. The useful answer is not my opinion — it is a method they can run themselves, on public records, in about ten minutes.

1. Find the developer’s own published date

Not the date a listing site repeats. The date the developer published, in a brochure, a filing or a press statement, with a date attached to it. Write it down along with where you found it. This is your baseline, and most people skip it.

2. Check the building permit record

Permits are dated and public. You are looking for two things: whether a vertical construction permit exists, and whether inspections are progressing through it. A permit issued eighteen months ago with no subsequent inspection activity is the clearest signal available that a project is not moving.

3. Look for a recorded construction loan

Large towers are not built out of deposits alone. A construction mortgage is recorded in the county’s official records and is searchable by the developer entity or the folio. Its presence is not a guarantee. Its absence, on a project claiming to be under construction, is a question you should get answered in writing.

4. Check whether the county has issued folios

When a condominium declaration is recorded, the Property Appraiser creates a folio for each unit. No folios means no recorded declaration, which means the building is not close to closing units, whatever the sales schedule says. It is a blunt instrument and a reliable one.

Then compare

Put the developer’s published date next to what the permits, the loan record and the folio status actually show. If they agree, you have a schedule. If they do not, you have a marketing document.

This is the same method behind our own tracker, which is why 22 of the 38 towers we follow are recorded as having moved a published date. None of that came from a source you cannot check yourself.

Frequently asked questions

Can I check a Miami construction schedule without a real estate agent?

Yes. Permits, recorded mortgages and Property Appraiser folio records are all public and searchable, and together they show whether a project is actually progressing.

What does it mean if a building has no folios yet?

It means no condominium declaration has been recorded for it. The building cannot close individual units until that happens, regardless of what the sales timeline says.

Is a missing construction loan always a problem?

Not always, but on a tower marketed as under construction it is the question most worth getting answered in writing before you commit a deposit.

Since2002Selling Miami luxury
Closed$1B+In career sales volume
Years24In this market
Buildings478Tracked across Miami

Sources and further reading

Direct line

Ask Josh a question

Tell me the building, the budget and the timeline. You will get an honest read — including when the answer is that you should not buy it.

+1 (305) 695-8257 · hello@joshsteinrealtor.comPhone or WhatsApp · English / Español · Licensed in Florida since 2002

The Miami Confidential

The reporting, every two weeks.

Every new case file. Every delivery date that moves. Every figure dated and sourced. No listings, no hype, no press releases dressed up as news.

Free, every two weeks. Pick one or both. Unsubscribe in one click.
A–Z Buildings
Scroll to Top