Latest File · Brickell & Brickell KeyThree Towers, and Nobody Can Tell You How Many Homes Are in ThemThis file needs no developer’s cooperation and makes no accusation. It is three towers, three sets of numbers …Open the files →
Josh Stein, Miami real estate associateJosh Stein

Mercedes-Benz Places Miami

Verified 4 August 2026Miami Pre-Construction Delivery Tracker5 sources

Sources

1 / 11

Mercedes-Benz Places Miami at dusk above Biscayne Bay — developer rendering

2 / 11

The garden pool at Mercedes-Benz Places Miami — developer rendering

3 / 11

The arrival and porte-cochere at Mercedes-Benz Places Miami — developer rendering

4 / 11

The residents' lobby at Mercedes-Benz Places Miami — developer rendering

5 / 11

A residence kitchen at Mercedes-Benz Places Miami — developer rendering

6 / 11

A bedroom at Mercedes-Benz Places Miami — developer rendering

7 / 11

A primary bathroom at Mercedes-Benz Places Miami — developer rendering

8 / 11

A residence living room over the bay at Mercedes-Benz Places Miami — developer rendering

9 / 11

A residence living and dining room at Mercedes-Benz Places Miami — developer rendering

10 / 11

The rooftop pool at Mercedes-Benz Places Miami — developer rendering

11 / 11

The public park at the base of Mercedes-Benz Places Miami — developer rendering

Building facts

Address
145, 155, 165 and 191 SW 12th Street, Miami, FL 33130
Neighborhood
Brickell / Southside Park
Year built
2028
Floors
67
Residences
800 across two towers, plus a 174-key hotel (JDS’s own site lists 821)
Developer
JDS Development Group · Michael Stern
Status
Stalled — partially built, work stopped amid litigation

Building facts

Address
145, 155, 165 and 191 SW 12th Street, Miami, FL 33130
Neighborhood
Brickell / Southside Park
Year built
Not announced
Floors
67
Residences
800 across two towers, plus a 174-key hotel (JDS’s own site lists 821)
Status
Stalled — construction halted; lender Cottonwood filed to foreclose April 2026 seeking $100M+, developer JDS countersuing
Developer
JDS Development Group · Michael Stern

Have a question about Mercedes-Benz Places Miami? This page is built from the county record and the trade press, not a listing feed. If you want what has actually closed here, or an honest read on whether it suits you, ask me directly.

Call (305) 695-8257Email about Mercedes-Benz Places Miami

Key Takeaways

  • 800 across two towers, plus a 174-key hotel (JDS’s own site lists 821) residences across 67 floors — at 145, 155, 165 and 191 SW 12th Street, Miami, FL 33130.
  • Status: Stalled — partially built, work stopped amid litigation — verified against the county roll and the development trade record.
  • Developed by JDS Development Group · Michael Stern.
  • Year built: 2028.

Mercedes-Benz Places Miami is in foreclosure and construction has stopped. In April 2026 an affiliate of Cottonwood Group filed suit in Miami-Dade Circuit Court seeking $80.4 million in principal plus interest and fees, with interest accruing at $53,621 per day. The bridge loan behind it matured on 15 January 2025 and was not repaid.

This page exists because a buyer considering a deposit here — or holding one — needs the actual record, not a rendering. Everything below is dated and sourced. If you have money in this building, the section on buyer rescissions is the one to read first.

Mercedes-Benz Places Miami — Building Facts

Address
145, 155, 165 and 191 SW 12th Street, Miami, FL 33130
Neighbourhood
Brickell / Southside Park
Developer
JDS Development Group · Michael Stern
Reported Incoming Partner
Fontainebleau Development (Jeff Soffer), reported June 2026 — not confirmed closed
Brand
Mercedes-Benz — licensed
Storeys
67 (Florida YIMBY describes two towers of about 64 each)
Residences
800 across two towers, plus a 174-key hotel (JDS’s own site lists 821)
Land Basis
Acquired by JDS in 2019 for $23.5M
Announced / Sales Launch
February 2024
Vertical Construction
Began on Tower 1, March 2025
Debt
$85M bridge loan from Maxim Credit Group — taken over 24 March 2026 by a Cottonwood Group affiliate
Loan Maturity
January 2025, after repeated extensions from late 2023 — not repaid
Foreclosure
Filed April 2026 — $80.4M principal plus ~$20M interest, close to $100M total; interest $53,621/day as of 30 Mar 2026
First Promised
2027
Current Delivery
2028 — and that figure predates the construction halt
Status
🔴 Stalled — partially built, work stopped amid litigation

Verified 4 August 2026 against The Real Deal, Bisnow and Florida YIMBY. Units sold and percentage in contract have never been published. The 2028 completion figure predates the construction halt and should not be relied on. This is an active, evolving legal matter — have counsel check the current docket.

What happened at Mercedes-Benz Places Miami, in order?

  • 2019 — JDS Development Group acquires the Southside Park site for $23.5 million.
  • An $85 million bridge loan is provided by Maxim Credit Group. Its maturity is repeatedly extended from late 2023.
  • February 2024 — the Mercedes-Benz branded project launches sales, promising delivery in 2027.
  • January 2025the bridge loan matures and is not repaid, after repeated extensions from late 2023.
  • March 2025 — vertical construction begins on Tower 1.
  • 24 March 2026 — the loan is taken over by CWRE SSF Flamingo Capital, an affiliate of Los Angeles-based Cottonwood Group.
  • April 2026foreclosure suit filed, seeking $80.4 million in principal plus interest and fees. A number of subcontractors have also filed liens against the project. Delivery guidance moves to 2028.
  • May 2026 — roughly 10 percent of unit buyers request rescission of their contracts. The Real Deal describes the two-tower project as partially built with work stopped amid the litigation.
  • June 2026 — the City of Miami notifies JDS of default under its public benefits agreement, which requires construction of an $8 million firehouse. Separately, Fontainebleau Development is reported as poised to join as a partner alongside a roughly $1.06 billion financing package involving BDT & MSD.

The Foreclosure

The numbers matter here, so take them slowly.

The original facility was $85 million from Maxim Credit Group, with a maturity repeatedly extended from late 2023. It matured in January 2025 and was not repaid. On 24 March 2026 the loan was taken over by CWRE SSF Flamingo Capital, an affiliate of Los Angeles-based Cottonwood Group, and in April 2026 that affiliate filed to foreclose. The claim is $80.4 million in principal plus nearly $20 million in interest — close to $100 million in total, with interest running at $53,621 a day as of 30 March 2026.

Alongside it, a number of subcontractors have filed liens against the project. The Real Deal does not give a count. That is the pattern you see when a project stops paying its trades.

JDS has countersued Cottonwood. This is contested litigation, not a settled outcome, and nothing on this page should be read as predicting how it resolves.

Interest on the defaulted loan was accruing at $53,621 per day as of 30 March 2026 — roughly $1.6 million a month — while construction is stopped.

The Real Deal, 6 April 2026

What This Means If You Have a Deposit In

I am not your lawyer and this is not legal advice. But if you are holding a contract here, these are the questions to take to counsel, in this order:

  • Where is your deposit held, and under what escrow terms? Florida’s condominium statute governs escrow for pre-construction deposits, and the answer depends on the specific language in your purchase agreement.
  • What is your outside date, and has it passed? Roughly 10 percent of buyers requested rescission after the foreclosure filing. Whether that right is available to you turns on your contract, not on the news.
  • Does a foreclosure or a change of sponsor trigger any right on your side? Ask specifically about lender-consent provisions and assignment clauses.
  • If a new partner recapitalises the project, what happens to your contract and your price? A rescue is not automatically a bad outcome for a buyer — but the terms are everything.

Do not take the answer from the sales office. Take it from a Florida real-estate attorney reading your actual contract. That is worth a few hundred dollars against a seven-figure deposit.

Inside the residences as planned

Interiors as the developer presented them before the foreclosure — renderings, not photographs.

A residence kitchen at Mercedes-Benz Places Miami — developer rendering
A residence kitchen at Mercedes-Benz Places Miami — developer rendering
A bedroom at Mercedes-Benz Places Miami — developer rendering
A bedroom at Mercedes-Benz Places Miami — developer rendering
A primary bathroom at Mercedes-Benz Places Miami — developer rendering
A primary bathroom at Mercedes-Benz Places Miami — developer rendering
A residence living room over the bay at Mercedes-Benz Places Miami — developer rendering
A residence living room over the bay at Mercedes-Benz Places Miami — developer rendering
A residence living and dining room at Mercedes-Benz Places Miami — developer rendering
A residence living and dining room at Mercedes-Benz Places Miami — developer rendering

The Possible Rescue

In June 2026 The Real Deal reported that Fontainebleau Development, Jeff Soffer’s firm, was poised to join the project as a partner alongside a financing package of roughly $1.06 billion involving BDT & MSD — against the $750 million package The Real Deal described in April 2026.

That has not been reported as closed. It is the most recent substantive development on the public record and it is genuinely significant — a sponsor of that scale and a facility of that size would change the picture entirely. But “poised to” is not “did,” and as of this writing no source confirms the deal closed, construction restarted, or the foreclosure resolved.

If you are watching this building, that is the single item to watch.

The amenity levels as planned

The pools, the screening room and the lobby, from the developer’s own materials.

The rooftop pool at Mercedes-Benz Places Miami — developer rendering
The rooftop pool at Mercedes-Benz Places Miami — developer rendering
The garden pool at Mercedes-Benz Places Miami — developer rendering
The garden pool at Mercedes-Benz Places Miami — developer rendering
The residents' lobby at Mercedes-Benz Places Miami — developer rendering
The residents' lobby at Mercedes-Benz Places Miami — developer rendering

What Was Planned

The scheme is two towers carrying 800 residential units and a 174-key hotel. JDS’s own website lists 821 residential units, which is unreconciled with the 800 reported by The Real Deal.

Sales launched in February 2024. No units-sold figure or percentage in contract has ever been published — in more than two years of selling, and through a foreclosure. That absence is itself informative.

Note also that JDS is the developer behind 888 Brickell by Dolce&Gabbana, which as of 8 July 2026 had still not closed construction financing and has never had vertical construction reported. Two JDS projects in Brickell, both stalled at the financing stage, is a sponsor-level pattern worth understanding before you sign anything with this developer.

The tower as planned

Mercedes-Benz Places shown from the bay, the park and the arrival.

Mercedes-Benz Places Miami at dusk above Biscayne Bay — developer rendering
Mercedes-Benz Places Miami at dusk above Biscayne Bay — developer rendering
The public park at the base of Mercedes-Benz Places Miami — developer rendering
The public park at the base of Mercedes-Benz Places Miami — developer rendering
The arrival and porte-cochere at Mercedes-Benz Places Miami — developer rendering
The arrival and porte-cochere at Mercedes-Benz Places Miami — developer rendering
Mercedes-Benz Places Miami at dusk above Biscayne Bay — developer rendering
Mercedes-Benz Places Miami at dusk above Biscayne Bay — developer rendering

Brickell Around It

The site sits at the western edge of Brickell around Southside Park, close to the Miami River and a short distance from Brickell City Centre and the Metromover Brickell Loop. It is a genuinely good location, which is part of why the land and the entitlements have value regardless of how the litigation resolves.

For context on how this project compares with the rest of the market, the Miami Pre-Construction Delivery Tracker records 38 South Florida towers: 22 have slipped at least once, 14 have no construction loan reported, and 5 — including this one — are stalled or in litigation.

Mercedes-Benz Places Miami — Frequently Asked Questions

Is Mercedes-Benz Places Miami still being built?

No. As of the most recent reporting the two-tower project is partially built with construction stopped amid litigation. Vertical construction began on Tower 1 in March 2025 and the project reached partial height before work halted.

What is the foreclosure about?

An $85 million bridge loan from Maxim Credit Group, whose maturity was repeatedly extended from late 2023, matured in January 2025 and was not repaid. On 24 March 2026 the loan was taken over by CWRE SSF Flamingo Capital, an affiliate of Los Angeles-based Cottonwood Group, which filed to foreclose in April 2026. The claim is $80.4 million in principal plus nearly $20 million in interest — close to $100 million in total — with interest accruing at $53,621 a day as of 30 March 2026. A number of subcontractors have also filed liens. JDS has countersued Cottonwood and is reported to be working on a $750 million replacement financing package.

I have a deposit in this building. What should I do?

Take your purchase agreement to a Florida real-estate attorney, not to the sales office. Ask where your deposit is held and under what escrow terms, what your outside date is and whether it has passed, whether a foreclosure or change of sponsor triggers any right on your side, and what happens to your contract and price if the project is recapitalised. Roughly 10 percent of buyers requested rescission after the April 2026 foreclosure filing; whether that right is available to you depends on your specific contract.

Could the project be rescued?

Possibly. In June 2026 The Real Deal reported that Fontainebleau Development, Jeff Soffer’s firm, was poised to join as a partner alongside a roughly $1.06 billion financing package involving BDT & MSD. That has not been reported as closed, and no source confirms construction has restarted or the foreclosure has resolved. It is the single item worth watching.

When was it supposed to be finished?

2027, promised at the February 2024 sales launch. Guidance moved to 2028 by April 2026 — but that figure predates the construction halt and should not be relied on.

How many units have sold?

Never published. In more than two years of selling, and through a foreclosure filing, no units-sold figure or percentage in contract has appeared in any source. That absence is itself worth noting.

Is the developer behind other Miami projects?

Yes. JDS Development Group is also the developer of 888 Brickell by Dolce&Gabbana, which as of 8 July 2026 had still not closed construction financing and has never had vertical construction reported by any credible source. Two JDS Brickell projects stalled at the financing stage is a sponsor-level pattern worth understanding.

Sources and further reading

Thinking about Mercedes-Benz Places Miami?

I have sold South Florida property since 2002, more than $1 billion of it. Ask me for the recorded declaration, what has genuinely closed, or a straight answer on whether this building fits what you are after.

Call (305) 695-8257Send me a question

Josh Stein · Florida real estate sales associate, license SL3057661 · (305) 695-8257 · hello@joshsteinrealtor.com
Ask me about Mercedes-Benz Places MiamiWhatsAppContact

Related coverage

Part of South Florida New Construction.

Direct line

Ask Josh a question

Tell me the building, the budget and the timeline. You will get an honest read — including when the answer is that you should not buy it.

+1 (305) 695-8257 · hello@joshsteinrealtor.comPhone or WhatsApp · English / Español · Licensed in Florida since 2002

The Miami Confidential

The reporting, every two weeks.

Every new case file. Every delivery date that moves. Every figure dated and sourced. No listings, no hype, no press releases dressed up as news.

Free, every two weeks. Pick one or both. Unsubscribe in one click.
A–Z Buildings
Scroll to Top